Bhubaneswar, Nov 21: In a major relief to a homebuyer, the Odisha Real Estate Appellate Tribunal (OREAT) has quashed an arbitrary price hike of approximately ₹21 lakh imposed by the Odisha State Housing Board (OSHB) on a four-bedroom deluxe flat at Kharavela Enclave in Jagamara, Bhubaneswar.
The tribunal ruled that the Housing Board could not increase the flat price from around ₹67 lakh to ₹88 lakh without providing any valid justification. Describing the hike as excessive and arbitrary, OREAT directed the cancellation of the increased amount and ordered the Board to pay compensation with interest for the delay in handing over possession.
The tribunal also directed OSHB to pay interest at an annual rate of 10.15 per cent for the delay in handing over the flat, calculated from June 13, 2017, the scheduled date of possession, until the actual handover.
Why did the tribunal cancel the ₹21 Lakh price hike?
The homebuyer had challenged the Housing Board's decision to substantially increase the price of the allotted flat without providing any proper explanation.
After examining the appeal, OREAT observed that OSHB could not arbitrarily revise the price of a flat from approximately ₹67 lakh to ₹88 lakh without establishing valid reasons for such a substantial increase.
The tribunal rejected the revised price, holding that the additional burden of nearly ₹21 lakh was unjustified.
Kharavela Enclave Project: A Long-Delayed Housing Project
The Odisha State Housing Board launched the Kharavela Enclave project in 2011. The project was registered under RERA in September 2018.
The buyer received a provisional allotment letter in June 2014 and had already paid ₹14.73 lakh towards the flat.
The tribunal observed that since construction had not been completed when the Real Estate (Regulation and Development) Act, 2016 came into force, the project fell within the ambit of the RERA Act.
OSHB's encroachment argument rejected
The Housing Board had argued that encroachment on the project land was an uncontrollable circumstance that contributed to the delay in construction and possession.
However, OREAT rejected this argument, observing that OSHB was already aware of the encroachment before inviting applications and accepting money from homebuyers.
Therefore, the Board could not subsequently cite the encroachment as an unforeseen or uncontrollable circumstance to justify the delay.
10.15% Interest for Delay in Possession
In another significant part of its order, the tribunal modified an earlier RERA direction issued in June 2019.
OREAT directed OSHB to pay interest at the rate of 10.15 per cent per annum as compensation for the delay in handing over possession.
The interest will be calculated from June 13, 2017, the originally scheduled possession date, until the actual date of handover.
Kharavela Enclave Was Earlier in the News Over Airport Height Restrictions
The Kharavela Enclave project had previously attracted attention after airport authorities raised objections over construction exceeding the prescribed height restrictions.
The issue reportedly contributed to prolonged construction delays.
Now, the project has returned to the spotlight following the OREAT ruling, which has questioned the Housing Board's arbitrary price revision and held it accountable for the delay in handing over possession.
The order is being seen as a significant relief for the affected homebuyer and a reminder that government housing agencies cannot impose unexplained price increases or evade responsibility for delays in delivering allotted flats.